Harrop Fold School (MITIE)

Project duration: 6 weeks
Project Budget: £160,000.00
Project Cost: £157,000.00

 

-Conversion of old ten centre
-Conversion of existing space to create 10nr classrooms
-Refurbishment of existing corridor and open the space up to link the existing school building
-Soundproofing of floor slab