Harrop Fold School (Manchester)

Project duration: 6 weeks
Project Budget: £160,000.00
Project Cost: £157,000.00

  • Conversion of old ten centre
  • Conversion of existing space to create 10nr classrooms
  • Refurbishment of existing corridor and open the space up to link the existing school building
  • Soundproofing of floor slab
Harrop Fold School construction project