Lister Community School (London)

Replacement Chiller (Lifecycle)

Project duration: 3 weeks
Project Budget: Undisclosed
Project Cost: £75,000.00

  • Removal of existing roof plant chillers
  • Design of new chiller to replace existing two with one that runs a lower environmental impact at high full and part load efficiency (design by GPJ Consulting Engineers Ltd)
  • CDM
  • Mechanical and electrical installation of new Carrier unit and pipework upgrades
  • BMS sytem upgrades
  • Testing and commisioning